Project Goals

Improve Vehicle Transit

  • Construct standard-width lanes
  • Install curb-and-gutter
  • Pedestrian safety
  • Eliminate mid-block crosswalk at Jordan Street
  • Construct 8’ multiuse path

Drainage

  • Construct all new drainage system
  • Provide future connection to stormwater drain from Stanley Road

Utilities

  • Replace aging emergency outfall line
  • Repair water and sewer lines

Aesthetics

  • Construct new board-on-board 6’ fence along entire southern edge of right-of-way
  • Regrade dry stormwater pond at Sandpiper Lane

Traffic detour map

DonnerDetourSpring2022

April 2021: Pre-bid Donner Road reconstruction plan sheets

Notice: April 28, 2021 public meeting

Additional Information on this project is presented in a slide show below and available as a pdf by clicking here.